Mitasny roadmap

# Task Status Work remaining Est. finish date
9 Generate weekly report Finished 0 11-20
10 Continuing-status Finished 0 11-20
11 Chart header to include dates Finished 0 11-20
12 Project CRUD Finished 0 11-20
13 User registration Finished 0 11-20
14 Reorder tasks Finished 0 11-20
15 Weekly report containing all projects Ongoing 1 11-21
16 SSL encryption Pending 1 11-22
17 Django allauth Pending 2 11-24
18 Add task to beginning Pending 1 11-27
19 Mark task as done Pending 1 11-28
20 Confirm that finished tasks have zero work remaining Pending 1 11-29
21 About page Pending 1 11-30
23 Option to show descriptions in task list Pending 1 12-01
24 Send weekly report as email Pending 3 12-06
25 Script to take screenshots of graphs Pending 1 12-07
26 Include graph screenshots in mail Pending 1 12-08
Total: 2 week(s), 4 day(s) 14 12-08