Mitasny roadmap

# Task Status Work remaining Est. finish date
9 Generate weekly report Finished 0 09-28
10 Continuing-status Finished 0 09-28
11 Chart header to include dates Finished 0 09-28
12 Project CRUD Finished 0 09-28
13 User registration Finished 0 09-28
14 Reorder tasks Finished 0 09-28
15 Weekly report containing all projects Ongoing 1 09-29
16 SSL encryption Pending 1 09-30
17 Django allauth Pending 2 10-04
18 Add task to beginning Pending 1 10-05
19 Mark task as done Pending 1 10-06
20 Confirm that finished tasks have zero work remaining Pending 1 10-07
21 About page Pending 1 10-08
23 Option to show descriptions in task list Pending 1 10-11
24 Send weekly report as email Pending 3 10-14
25 Script to take screenshots of graphs Pending 1 10-15
26 Include graph screenshots in mail Pending 1 10-18
Total: 2 week(s), 4 day(s) 14 10-18