Mitasny roadmap

Last week This week Backlog
Task Days  
Weekly report containing all projects 1   07-18
SSL encryption 1     07-19
Django allauth 2         07-23
Add task to beginning 1           07-24
Mark task as done 1             07-25
Confirm that finished tasks have zero work remaining 1               07-26
About page 1                 07-27
Option to show descriptions in task list 1                   07-30
Send weekly report as email 3                         08-02
Script to take screenshots of graphs 1                           08-03
Include graph screenshots in mail 1                             08-06
  17
7
18
7
19
7
20
7
23
7
24
7
25
7
26
7
27
7
30
7
31
7
1
8
2
8
3
8
 
Total 14 Estimated finish date: 2018-08-06

Estimated total work required by remaining tasks: 2 week(s), 4 day(s)

CVDB roadmap

Last week

Estimated total work required by remaining tasks: 0 day(s)